The Kosmoport mall’s ventilation system

Characteristics

Faced with a tight 1.5-month timeframe and a nearly complete building, we were tasked with installing air handling units of a specific size into the existing ventilation chamber.
This presented a significant challenge given the typical manufacturing lead time for such equipment.

To overcome this hurdle, we redesigned the original solution, replacing the planned equipment with energy-efficient heat recovery units.

This not only met the tight deadline but also reduced operating costs
This not only met the tight deadline but also reduced operating costs
and improved the overall energy efficiency of the building.

Air Conditioning